Photos
20
This Week
0
Defects
2
Client Ready
17

Exterior complete, landscaping finished, ready for handover

Unit A | hallway
Hallway with timber flooring laid and painted walls

Unit A | bedroom
Master bedroom Unit A, carpet laid, wardrobe doors installed

Unit A | living
Living area painting and flooring complete

Unit A | kitchen
Kitchen fully installed with appliances and splashback

Unit A | bathroom
Bathroom fit-off complete, vanity and mirror installed

Unit B | bathroom
Water staining on ceiling below Unit B bathroom, possible waterproofing failure

Unit A | kitchen
Kitchen cabinets and stone benchtop installed Unit A

Unit A | living
Interior painting complete Unit A living area, white walls

Unit A | bathroom
Cracked tile near shower drain, needs replacement

Unit A | ensuite
Floor tiles laid in Unit A ensuite, grouting in progress

External cladding and windows installed, scaffolding still up

Unit A
Switchboard installed and wired, meter box ready

Roof tiles installed, ridge capping complete

Unit A | kitchen
Electrical rough-in wiring through wall cavities

Unit A | ensuite
Plumbing rough-in complete, all pipes capped and pressure tested

Scaffolding erected around building for upper floor work

Unit A | bathroom
Copper pipe rough-in Unit A bathroom, hot and cold lines capped

Unit B | living
Unit B framing complete, ready for roof

Unit A | living
Wall frames up for Unit A, roof trusses being installed